Timeline

Scroll through the timeline below for more information on all the engagement so far as well as download links to all our previous materials.

October 2020

Council’s Response and Recovery Committee makes the decision to proceed with the redevelopment of the Kingfisher Leisure Centre and the Cattle Market car park.

Download the Committee report on the closure of the Kingfisher on our website.

March-April 2021

Early listening phase on the Kingfisher, Cattle Market car park and Guildhall complex sites.

Download a summary of our engagement here.
Download a copy of our flyer here.

May 2021

Strategic Outline Business Case for the redevelopment of the Kingfisher Leisure Centre and Cattle Market sites is accepted by the council’s Response and Recovery Committee.

Download the Business Case document here.

July – August 2021

Engagement on proposals for the Kingfisher Leisure Centre and early plans for the Cattle Market car park site.

Download a summary of our engagement here.
Download a copy of our newsletter here.

1 September 2021

Local Planning Authority approves application to demolish Kingfisher Leisure Centre, making way for a durable, community leisure facility for Kingston.

November – December 2021

Phase 3 of engagement on the latest designs for the Kingfisher Leisure Centre.

Find out more about our engagement events here.
Take part in our public survey until the 31st December here.
Download a copy of our newsletter here.

2023

Subject to planning permission, construction expected to start on the Kingfisher site.

2024

New leisure facility opens.